Solihull-based firm Armac removed a 4,000 tonne bridge over the M42- and carried out the demolition ahead of schedule
A team of 20 demolition experts from Solihull-based firm Armac, working on behalf of HS2’s main works contractor in the Midlands, Balfour Beatty VINCI (BBV), carried out the M42 bridge demolition in a 52 hour operation.
The operation was coordinated in conjunction with National Highways, with contractors working throughout the night to prepare the area for the demolition activities.
4,000 tonnes, 8 excavators and six dumper trucks
Starting at 7am on Saturday 10 February, the demolition team used a 100 tonne excavator and a further seven 50 tonne demolition excavators to complete the operation, supplemented by numerous breaker and cruncher attachments.
Six articulated dumper trucks transported the excavated material to a local stockpile where it will be crushed and reused on HS2’s haul roads and work sites.
Once the bridge was demolished at around 3pm on Saturday, the debris was removed, the matting taken away, carriageway cleaned, and central reservation and verge restraint systems reinstated, ready for the motorway to be re-opened at 1.30am on Monday 12 February.
Another successful project from the Bridge Busters
Oliver Shore, construction director at Balfour Beatty VINCI said: “The safe and successful demolition of this 4,000-tonne bridge is another huge achievement for Balfour Beatty VINCI. This was a complex operation, made even more challenging because of the limited time we had to plan and deliver this critical work. I’m really proud of how the team responded, showcasing their skill and experience in these demanding circumstances.
“It’s the second bridge removal we’ve delivered along the same stretch of motorway in just six months. Like the previous demolition last summer, every effort was made to minimise the impact on road users through careful planning and close collaboration between HS2 and National Highways.”
Noel McLean, technical director of Armac said: “We were delighted to work with our partners HS2 and BBV again, for the demolition of the M42 North Bridge. Our primary aim is always to complete the project safely and in a controlled operation. Thankfully, the project was completed well ahead of schedule. Another successful project from the Armac ‘Bridge Busters’ and all of the BBV team.”
Construction will commence on the twin box structure later this year
It is the second of two 4,000 tonne bridges in close proximity over the M42 which needed to be demolished so HS2 can build a new twin box structure, which will carry the high speed line over the motorway in the future. The operation by Armac to demolish the first bridge took place in August last year.
The original plan was to demolish the second bridge next year. However, due to two drivers on the motorway below recently striking the bridge, National Highways asked HS2 to demolish the bridge sooner because it had become unsafe.
This new structure, measuring 300 metres length by 25 metres width will cover around 130 metres of the M42 and will be built in position whilst maintaining three lanes of traffic flowing on the M42.
Piling is due to start in August
This section of HS2 railway lies between Interchange Station in Solihull and the Delta Junction, a triangular section of the line which enables trains to either travel into Birmingham’s Curzon Street Station or carry on north where trains will join the West Coast Main Line to Manchester.